NEC 700 is the article for emergency systems: power and lighting that a building code or government agency requires to keep people alive when the normal supply fails, such as egress lighting and exit signs. They must pick up within 10 seconds. Articles 701 (legally required standby, 60 seconds) and 702 (optional standby, no time limit) cover the two other kinds of backup power, and the exam expects you to tell them apart instantly.

This guide compares the three articles side by side, then goes through each one: definitions, transfer times, power sources, wiring separation, marking, testing and selective coordination. Worked examples and exam-style questions show how test writers turn those rules into points.

Emergency vs standby: the three systems at a glance

The deciding questions are always the same: who requires the system, and what does it protect?

Article 700 EmergencyArticle 701 Legally required standbyArticle 702 Optional standby
Required byA code or governmental agency, classed as emergencyA code or governmental agency, classed as legally required standbyNobody (owner's choice)
ProtectsHuman life directlySelected loads that support safety, firefighting or rescueProperty, business, comfort
Typical loadsEgress lighting, exit signsSmoke control, sewage disposal, communicationsWhole house, data processing, refrigeration, farms
Power available within10 seconds60 secondsNo requirement
TransferAutomaticAutomaticAutomatic or manual
WiringKept independent of all other wiringMay share raceways with general wiringMay share raceways with general wiring
Selective coordinationRequired (700.32)Required (701.32)Not required
Witness test by AHJYesYesNo
0 s10 s60 sArt. 700Emergency: 10 s max.Art. 701Legally required standby: 60 s max.Art. 702Optional standby: no time requirement
Maximum time from loss of normal power until the alternate source must be supplying the load.

NEC 700: emergency systems

Emergency systems are legally required and classed as emergency by a municipal, state, federal or other code, or by a governmental agency having jurisdiction. They automatically supply illumination, power or both to designated areas and equipment when the normal supply fails, where that power is essential for safety to human life.

Typical emergency loads are egress lighting and exit signs in places of assembly, and in some buildings ventilation essential to life, fire detection and alarm systems, elevators, fire pumps or public safety communications, when the governing code classes them as emergency.

Timing: 10 seconds

NEC 700.12: emergency power must be available within the time required for the application, but not more than 10 seconds after the normal supply fails.

Power sources

NEC 700.12 lists the sources that may supply an emergency system. Each must be suitable for the load and approved for the purpose:

  • Storage batteries sized to carry the total load for at least 1½ hours without the voltage at the load falling below 87½% of normal.
  • Generator sets. Where an internal combustion engine is the prime mover, an on-premises fuel supply for at least 2 hours of full-demand operation is required.
  • Uninterruptible power supplies that meet the battery and source requirements.
  • A separate service, where acceptable to the authority having jurisdiction.
  • Fuel cell systems and other listed sources the section recognizes.
  • Unit equipment: individual battery-powered emergency lights, each with its own battery, charger and automatic transfer, also rated for at least 1½ hours.

Transfer equipment

NEC 700.5: transfer equipment must be automatic, identified for emergency use and approved by the authority having jurisdiction. It supplies only emergency loads. In practice, that means a dedicated automatic transfer switch (ATS) for the emergency branch, separate from any standby loads.

Wiring: kept independent

NEC 700.10(B) requires the wiring from the emergency source or emergency source distribution overcurrent protection to emergency loads to be kept entirely independent of all other wiring and equipment. Limited exceptions include wiring in transfer equipment enclosures, exit and emergency luminaires supplied from two sources, and a common junction box attached to unit equipment.

Boxes and enclosures for emergency circuits, including transfer switches, generators and power panels, must be permanently marked so they are readily identified as part of an emergency circuit or system (NEC 700.10(A)).

Fire protection of feeders

In certain occupancies, emergency feeder-circuit wiring must be protected from fire, for example with a 2-hour fire-rated cable system or by installation in spaces fully protected by an automatic fire suppression system. NEC 700.10(D) applies it to:

  • Assembly occupancies for not less than 1000 persons
  • Buildings above 75 feet in height
  • Health care occupancies where persons are not capable of self-preservation
  • Educational occupancies with more than 300 occupants

Signals, signs and testing

  • Signals (700.6): audible and visual devices, where practicable, to show derangement of the emergency source, that the battery or generator is carrying load, and charger malfunction.
  • Signs (700.7): a sign at the service entrance equipment indicating the type and location of each on-site emergency power source.
  • Tests (700.3): the entire system must be tested in the presence of the authority having jurisdiction on completion (a witness test) and periodically afterward, with a written record of tests and maintenance kept.

Capacity and load shedding

NEC 700.4: the emergency system must have adequate capacity for all loads expected to operate at the same time. One alternate source may supply emergency, legally required standby and optional standby loads, but only with automatic selective load pickup and load shedding that guarantees power in this priority: 1) emergency, 2) legally required standby, 3) optional standby.

Selective coordination

NEC 700.32: emergency system overcurrent devices must be selectively coordinated with all supply-side and load-side overcurrent devices, so a fault opens only the device closest to it and the rest of the emergency system stays energized. The 2023 NEC added that coordination must be re-evaluated when those overcurrent devices are replaced, and when the emergency system is modified, added to or reduced. Coordination is a breaker and fuse selection issue; see overcurrent protection under 240.4 and standard breaker sizes for the basics.

NEC 701: legally required standby systems

Legally required standby systems are also required by a code or governmental agency, but they supply selected loads other than emergency loads. They support safety indirectly: if those loads stop, they could create hazards or hamper rescue or firefighting.

Typical loads: heating and refrigeration systems, communication systems, ventilation and smoke removal systems, sewage disposal, lighting systems, and industrial processes whose interruption could create hazards.

The key differences from Article 700:

  • 60 seconds instead of 10 (NEC 701.12).
  • Wiring may share raceways, cables, boxes and cabinets with general wiring (NEC 701.10). No separation requirement.
  • Transfer equipment must be automatic and identified for standby use (NEC 701.5).
  • Selective coordination is still required (NEC 701.32), with the same 2023 re-evaluation rules.
  • Witness testing and periodic testing are required (NEC 701.3), and a sign at the service entrance shows the type and location of the source (NEC 701.7).

NEC 702: optional standby systems

Optional standby systems supply facilities or property where life safety does not depend on the system. They provide on-site power to selected loads, automatically or manually. Examples include data processing and communication systems, commercial and farm operations, and the home standby generator.

The rules focus on making the connection safe and the system adequate:

  • Transfer equipment (702.5): required for any connection to premises wiring, to prevent inadvertent interconnection of the normal and alternate sources. An interconnection with the utility that operates in parallel must follow Article 705 instead.
  • Capacity (702.4): with manual transfer, the system must supply all equipment intended to operate at one time (the user picks the loads). With automatic transfer, it must supply the full load that is automatically transferred, unless an energy management system limits the load, in which case it must supply the maximum load the EMS will connect. Load calculations follow Article 220.
  • Signs (702.7): a sign at the service entrance indicating the type and location of the on-site optional standby source. Where a portable generator connects through a power inlet, a warning sign near the inlet tells the user which type of generator (bonded or floating neutral) the transfer equipment is wired for.
  • No time limit, no selective coordination requirement, no separation requirement.

Wiring may NOT share raceways

  • Article 700 emergency circuits
  • Kept entirely independent (700.10(B))
  • Limited exceptions: transfer switch enclosure, two-source luminaires, unit equipment junction box

Wiring MAY share raceways

  • Article 701 legally required standby
  • Article 702 optional standby
  • Same raceways, cables, boxes and cabinets as general wiring

Worked examples, built like exam questions

Worked example

Classify the loads

  1. 1

    The question

    A new building has (a) egress lighting required by the building code, (b) smoke-control fans required by the building code and classed as legally required standby, and (c) a server room the owner wants backed up. Which NEC article covers each, and what is the maximum transfer time?

  2. 2

    Egress lighting

    Required by code and essential to human life: Article 700, within 10 seconds.

  3. 3

    Smoke control

    Required by code, classed as legally required standby: Article 701, within 60 seconds.

  4. 4

    Server room

    Owner's choice, life safety does not depend on it: Article 702, no time requirement.

  5. ✓ Answer: (a) Art. 700, 10 s; (b) Art. 701, 60 s; (c) Art. 702, no time limit. Each typically gets its own transfer switch.
Worked example

One generator, three systems: load shedding

  1. 1

    The question

    A single 60 kW generator supplies 20 kW of emergency load, 30 kW of legally required standby load and 25 kW of optional standby load, through automatic load pickup and shedding. Which loads are guaranteed?

  2. 2

    Total connected

    20 + 30 + 25 = 75 kW, more than the 60 kW available.

  3. 3

    Apply the priority from 700.4

    Emergency first: 20 kW. Legally required standby next: 20 + 30 = 50 kW. Optional standby gets what is left: 60 − 50 = 10 kW.

  4. ✓ Answer: Emergency and legally required standby loads (50 kW) are fully supplied. Only 10 kW of the 25 kW optional load can be picked up; the rest must be shed.

Practice: emergency and standby exam questions

Exam-style question

Emergency system power must be available within a maximum of how many seconds after failure of the normal supply?

Pick an answer to see the explanation.

Exam-style question

Which statement about legally required standby system wiring is correct?

Pick an answer to see the explanation.

Exam-style question

A homeowner installs an automatic standby generator that transfers the entire service panel. Under Article 702, the generator must be sized to supply:

Pick an answer to see the explanation.

The mistakes that cost points

Classifying by importance instead of by code requirement. A hospital data room feels important, but unless a code requires it and classes it, it is not an emergency system. The classification comes from the requiring code, not the size or cost of the load.

Swapping 10 and 60 seconds. Emergency is 10. Legally required standby is 60. Optional has none.

Running emergency circuits in shared raceways. Only 701 and 702 wiring may share. Emergency wiring is independent.

Forgetting selective coordination for 701. It applies to both 700 and 701, not only to emergency.

Ignoring load-shedding priority. Emergency, then legally required standby, then optional.

Calling a home generator "emergency". It is optional standby under Article 702.

NFPA 110: Type, Class and Level

The NEC tells you how to wire the system. NFPA 110 (Standard for Emergency and Standby Power Systems) governs the generator installation's performance, and its vocabulary shows up on specs, generator nameplates and some master exams. It rates a system three ways:

NFPA 110 termWhat it meansExample
TypeMaximum seconds without power after the normal source failsType 10 = 10 seconds (matches NEC 700.12)
ClassMinimum hours the system runs at rated load without refuelingClass 2 = 2 hours (matches the 2-hour fuel rule)
LevelHow critical the loads areLevel 1 = failure could cost human life; Level 2 = less critical

A spec that says "Level 1, Type 10, Class 2" is describing a typical Article 700 emergency generator. The weekly inspection and monthly load testing that keep it ready also come from NFPA 110, not from the NEC.

Several other articles connect to these three:

  • Article 517 (health care facilities) uses its own essential electrical system, split into life safety, critical and equipment branches, which builds on Article 700 and 701 concepts.
  • Article 695 (fire pumps) has its own power source and protection rules; a fire pump is not simply another emergency load.
  • Article 445 (generators) covers the generator itself: conductor sizing, overcurrent protection and disconnecting means.
  • Article 705 applies when a source runs in parallel with the utility instead of transferring.

Many jurisdictions adopt NFPA 110 alongside the NEC; see the NFPA 110 page. For a plain-language overview of all three articles, EC&M's NEC requirements for emergency and standby systems is a good second read.

How to find it fast in the code book

Articles 700, 701 and 702 sit together in Chapter 7. Tab 700 and highlight 700.10(B) (independent wiring), 700.12 (10 seconds and the sources), 700.4 (priority) and 700.32 (coordination). In 701, highlight 701.10 (shared raceways allowed) and 701.12 (60 seconds). In 702, highlight 702.4 (capacity). The code book tabbing guide shows how to color-code Chapter 7.

→Special topics hubWorking Clearance Around Electrical Panels: NEC 110.26

Transfer switches and generator disconnects need full working space too, so pair this guide with working clearance under NEC 110.26. Generators feeding fuel-handling or process areas may also sit near hazardous (classified) locations. The service side, where the required signs go, is covered in service-entrance conductors. Then take a timed set on the free journeyman practice test.